What type of building inspection is typically conducted once the framing is complete?

Prepare for the North Carolina Contractors Carpentry and Building Construction Exam. Study with flashcards and multiple choice questions that include hints and explanations to ensure exam success!

The correct choice is the rough-in inspection. This type of inspection takes place after the framing of a building is complete but before the walls are closed up with drywall or other finishes. During the rough-in inspection, the building inspector checks the structural integrity of the framing, along with the installation of essential components such as plumbing, electrical, and HVAC systems that are hidden within the walls or ceilings.

This inspection is crucial because it ensures that all the mechanical systems comply with local codes and standards while also verifying that the framing is correctly aligned and secure. The rough-in inspection is an important step in the overall construction process, as it allows contractors to address any issues before they become more complicated and costly to fix once the enclosure is complete.

The final inspection occurs after all work has been completed, while a site inspection is generally an initial assessment of the property prior to any construction. The environmental impact inspection focuses on how the construction affects the surrounding environment, which does not pertain specifically to the framing stage.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy